  • Client:
    Northern Police Treatment Centres
  • Sector:
    Residential Care
  • Type:
    Fully Designed Project
  • Procurement Method:
    Tendered
  • Location:
    Harlow Moor Road, Harrogate
  • Project Value:
    £1.23m

Project Description

Pacy and Wheatley completed a Retail and Leisure Construction and Refurbishment in Harrogate which comprised of the internal remodelling of live treatment centre with new build physio department.

The project was spread over ten phased completions beginning with demolition throughout the Christmas period whilst the centre was closed, to minimise noise for patients and residents.

Following demolition, staged commencement and completion dates of the various phases for refurbishment included nurses consulting rooms, meeting rooms, snooker rooms, internet cafe, changing rooms, gymnasium, hydrotherapy area and swimming pool. A new build state of the art physio department housing 18 beds and decorative exposed gluelam truss structure.

The Challenge

Carry out works without hindrance to operation of the facility

Carry out extensive demolition and install specialist steel supports over the short Christmas period.

Programming the works to ensure dates are met to ensure centre can operate to maximum capacity throughout the works.

Internal and external works being carried out concurrently.

Deal with design alterations throughout the project including extra works instructed of £230k.

The Solution

The “solutions meetings” were held with the facility management team each morning to discuss areas of work and noise levels

Protection to all adjacent surfaces and cordoned off areas whilst working to maintain cleanliness.

Meetings with sub contractors held to discuss areas of works and duration on a daily basis.

Two competent site managers were required to keep external and internal progress to the required programme.

Arranging timely meetings with design team prior to commencement of each phase and addressing access and egress.

Reviewing phase completion dates and updating of programme for discussions with clients.

Key Achievements

Incorporating a significant amount of extra works within the programme period.

Efficient management of extra works and late changes together with costings for informed decisions by the client.

Zero reportable accidents due to good H&S management.

High standard of finish attained with close liaison between Project Manager, Site Managers and supply chain.

PWC Downloadable Ebook

Free Brochure

Read more about what we do and how we can help with the smooth operation of your business. Download our printable eBook, perfect for reading on the go, which is available 24/7, for further information please use one of our contact forms.

Fill in a few details below to view our downloadable brochure.

Fields marked with an * are required.

Please see our Privacy Policy for further details on how we use your data.

Ebook Preview page 1 Ebook Preview page 2 Ebook Preview page 3